Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

3.2.7.9.(1)
OS1OP1OP3OS3
ObjectiveOP1 Fire Protection of the Building
Attribution
Application
Application 1: 
Design, with respect to the minimum duration of operation under a full load, of emergency generator power supplies for:
  • elevators:
    • serving storeys above the first storey in a building that is more than 36 m high measured between grade and the floor level of the top storey, and
    • for firefighters in conformance with Sentence 3.2.7.9.(2),
  • water supply for firefighting in conformance with Article 3.2.5.7., where the supply is dependent on electrical power supplied to the building,
  • fans and other electrical equipment that are installed to maintain the air quality specified in Article 3.2.6.2., and
  • fans required for venting by Article 3.2.6.6.
This applies to buildings described in Sentence 1.3.3.2.(1) of Division A.
Top of Page
Intent
Intent 1: 
To limit the probability that, during a failure of the normal power supply in a fire emergency situation, emergency generator power supplies to certain building services will not be capable of performing their intended functions for a length of time sufficient for emergency responders to carry out their duties, which could lead to:
  • the inability of elevator systems to be used in emergency response operations, which could lead to delays in emergency response operations,
  • firefighting operations being ineffective, which could lead to the fire not being controlled or suppressed, and
  • the inability of smoke management systems to control smoke conditions, which could lead to delays in emergency response operations.
This is to limit the probability of the spread of fire, which could lead to damage to the building.