Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
3.2.7.9.(2) | Application | Intent |
OS1 | OP1 | OS3 |
Objective | OS1 Fire Safety |
Attribution | |
Application | Application 1: Design, with respect to the minimum duration of the
simultaneous operation under a full load of all elevators for firefighters
plus one additional elevator, of emergency generator power supplies for elevators
required by Clause 3.2.7.9.(1)(a):
Exceptions:
except as exempted in Sentence 3.2.7.9.(3), which applies
when the time to recall all elevators under emergency power supply is not
more than 5 min.
|
Top of Page | |
Intent | Intent 1: To limit the probability that, during a failure of the normal
power supply in a fire emergency situation, emergency generator power supplies
to elevators will not be capable of performing their intended functions for
a length of time sufficient for emergency responders to carry out their duties,
which could lead to the inability of elevator systems to be used in emergency
response operations, which could lead to delays in emergency response operations,
which could lead to:
Intent 2: To clarify that the emergency generator power supply required
by Clause 3.2.7.9.(1)(a) is required to simultaneously operate all elevators
for firefighters plus one additional elevator for recall. |
Top of Page |