Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

8.2.1.1.(1)
++
Attribution
(a),(b),(c)
Application
Application 1: 
Covered ways to protect the public, where construction may constitute a hazard to the public.
Exceptions: 
except where:
  • the work is done within a solid enclosure,
  • the building is at a distance of 2 m or more from a public way used by pedestrians, or
  • site conditions warrant a distance greater than provided in Clause 8.2.1.1.(1)(b).
This applies to sites where buildings are undergoing construction, alteration or repair, including any incomplete or abandoned buildings.
Top of Page
Intent
Intent 1: 
To waive the need for a covered way to protect the public if certain conditions are met:
  • the work is undertaken within a solid enclosure so that persons are not exposed to a hazard, or
  • the work is sufficiently set back from a public way to minimize the hazard to persons using the public way.