Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

9.20.14.1.(1)
OS2OP2OH1OS1OH4OS3
ObjectiveOP2 Structural Sufficiency of the Building
Attribution
[F20,F80-OP2.3] Applies to elements that support or are part of an environmental separator or are exposed to moisture.
Application
Application 1: 
Minimum temperature, during and following installation, of mortar and masonry, including mortar and masonry in foundations, in buildings to which Part 9 applies [see Sentence 1.3.3.3.(1) of Division A for application of Part 9]:
  • where the wall height above the foundation wall does not exceed 11 m, and
  • in which the roof or floor system above the first storey is not of concrete construction.
Top of Page
Intent
Intent 1: 
To limit the probability of inadequate curing conditions, which could lead to a weak mortar-to-masonry bond or an inadequate resistance to freeze-thaw stresses.
This is to limit the probability of:
  • compromised structural integrity of masonry construction,
  • where masonry construction is part of an environmental separator, the displacement or failure of required environmental separation elements, which could lead to deterioration,
  • in assemblies exposed to moisture or the exterior, damage and deterioration, or
  • an inability to resist expected loads, which could lead to:
    • the excessive movement or deformation of walls, or
    • the excessive deflection or vibration of floors.
This is to limit the probability of:
  • the space being unsuitable for its intended use,
  • compromised operation of windows or doors, or
  • damage to the building.
Top of Page