Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
9.27.4.2.(1) | Application | Intent |
OH1 | OS2 |
Objective | OS2 Structural Safety |
Attribution | |
Application | Application 1: Caulking [required by Article 9.27.4.1.],
for buildings to which Part 9 applies [see Sentence 1.3.3.3.(1) of Division A for application of Part 9]:
|
Top of Page | |
Intent | Intent 1: To limit the probability of the premature failure of the
caulking joint under expected loads, which could lead to precipitation or
meltwater ingress, which could lead to deterioration, which could lead to
the structural failure of exterior walls or elements protected by exterior
walls, which could lead to harm to persons. |
Top of Page |