Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
5.7.1.1.(3) | Application | Intent |
OH1 | OS2 |
Objective | OH1 Indoor Conditions |
Attribution | |
Application | Application 1: Building location, site
grading, installation of catch basins on the building site,
and construction of foundation walls, where it
can be demonstrated that the building is designed
to accommodate extended exposure to water or the ingress of water.
This applies to buildings to which Part
5 applies [see Sentence 1.3.3.2.(1) of Division A for application of
Part 5].
|
Top of Page | |
Intent | Intent 1: To exempt from the application of Sentence 5.7.1.1.(1) and Clause 5.7.1.1.(2)(a) buildings that are specifically designed to accommodate
the accumulation of water at the building or the ingress of water.
Intent 2: To limit the probability of damage to moisture-susceptible
materials, which could lead to:
This is to limit the probability of:
This is to limit the probability of harm to persons.
|
Top of Page |