3.2.2.52.(2)

Objective

OS1 Fire Safety

Attribution

(b),(c)[F04-OS1.3]

Intent

Intent 1:

To limit the probability that loadbearing walls, columns and arches exposed to fire will prematurely fail or collapse, which could lead to the failure or collapse of a supported mezzanine during the time required to achieve occupant safety and for emergency responders to perform their duties, which could lead to harm to persons.

Intent 2:

To limit the probability that a mezzanine exposed to fire will prematurely fail or collapse during the time required to achieve occupant safety and for emergency responders to perform their duties, which could lead to harm to persons.

Top of Page