9.15.2.3.(4)

Objective

OP2 Structural Sufficiency of the Building

Attribution

[F20,F22-OP2.3]Applies to elements that support or are part of an environmental separator.

Intent

Intent 1:

To limit the probability of the inappropriate orientation of concrete blocks, which could lead to:

  • piers tilting or toppling, or
  • the structural failure of piers under gravity loads.

This is to limit the probability of compromised structural integrity, which could lead to:

  • structural failure,
  • where elements support or are part of an environmental separator, the displacement or failure of required environmental separation elements, which could lead to the deterioration of building elements, or
  • an inability to resist expected loads, which could lead to
    • the excessive deformation or deflection of walls, or
    • the excessive deflection or vibration of floors.

This is to limit the probability of:

  • the space being unsuitable for its intended use, or
  • damage to the building.