9.22.9.4.(1)

Objective

OP1 Fire Protection of the Building

Attribution

(a),(b)[F01-OP1.1]

Intent

Intent 1:

To limit the probability that an inadequate clearance will lead to heated air flowing from heat-circulating duct openings and overheating combustible material, which could lead to the ignition of combustible building components, which could lead to damage to the building.