9.26.4.6.(1)

Objective

OP1 Fire Protection of the Building

Attribution

[F61-OP1.1]Applies where a built-up roof intersects with a masonry chimney.

Intent

Intent 1:

Where the intersection is between a built-up roof and a chimney, to limit the probability of:

  • cracking, tearing or shrinking of built-up roof membranes (when returned up walls at a sharp angle),
  • interruption of roofing membranes at junctions with walls or chimneys, or
  • water temporarily ponding and eventually overtopping cant strips.

This is to limit the probability of water ingress into chimneys, which could lead to damage to masonry or to chimney liners from freeze-thaw stresses, which could lead to the escape of heat or flames, which could lead to the ignition of combustible building components, which could lead to damage to the building [see analysis for Sentence 9.21.4.6.(1)].

Top of Page