4.2.2.3.(1)

Objective

OP2 Structural Sufficiency of the Building

Attribution

Intent

Intent 1:

To limit the probability that:

  • the ground conditions will not be consistent with the design, and
  • excavation, dewatering and construction will not be carried out in accordance with the design and good engineering practice.

This is to limit the probability of excessive ground movements, which could lead to damage to the building.

Intent 2:

To facilitate, through qualification of persons involved with the review, the determination of compliance with this requirement.

Top of Page