9.15.3.2.(2)

Objective

OP2 Structural Sufficiency of the Building

Attribution

[F21-OP2.3]Applies to elements that support or are part of an environmental separator.

Intent

Intent 1:

To limit the probability that the weathering of pyritic material will lead to the heaving of footings, which could lead to the movement or cracking of foundation walls.

This is to limit the probability of:

  • compromised structural integrity of the foundation or supported elements,
  • where elements support or are part of an environmental separator, the displacement or failure of required environmental separation elements, which could lead to the deterioration of building elements, or
  • an inability to resist expected loads, which could lead to
    • the excessive deformation or deflection of walls, or
    • the excessive deflection or vibration of floors.

This is to limit the probability of:

  • the space being unsuitable for its intended use, or
  • damage to the building.

Top of Page