Sentence 9.20.12.3.(2)

  1. OH1
  2. OS2
  3. OP2

Objective

OP2 Structural Sufficiency of the Building

Attribution

[F20-OP2.3]Applies to elements that support or are part of an environmental separator.

Intent

Intent 1:

To limit the probability of excessive eccentricity of loads, which could lead to masonry cracking or falling.

This is to limit the probability of:

  • compromised structural integrity of masonry construction,
  • where masonry construction is part of an environmental separator, the displacement or failure of required environmental separation elements, which could lead to deterioration, or
  • an inability to resist expected loads, which could lead to:
    • the excessive movement or deformation of walls, or
    • the excessive deflection or vibration of floors.

This is to limit the probability of:

  • the space being unsuitable for its intended use,
  • compromised operation of windows or doors, or
  • damage to the building.

Intent 2:

To clarify the method for measuring the projection, beyond its supporting base, of rough-stone veneer where the face is not coplanar.

Top of Page