Sentence 9.20.13.7.(1)

  1. OH1
  2. OS2
  3. OP2
  4. OS1

Objective

OP2 Structural Sufficiency of the Building

Attribution

Intent

Intent 1:

To limit the probability of precipitation or meltwater ingress, or compromised thermal performance of components intended to resist heat transfer.

This is to limit the probability of:

  • the deterioration of masonry due to freeze-thaw stresses, or
  • the deterioration of masonry elements, which could lead to compromised structural integrity.

This is to limit the probability of damage to the building.

Top of Page