Sentence 9.20.13.8.(1)

  1. OS2
  2. OP2
  3. OH1
  4. OS1

Objective

OP2 Structural Sufficiency of the Building

Attribution

Intent

Intent 1:

To limit the probability of inadequate provision for drainage, which could lead to water pooling in cavities or air spaces for extended periods.

This is to limit the probability of:

  • the deterioration of masonry due to freeze-thaw stresses, or
  • the deterioration of masonry elements, which could lead to compromised structural integrity.

This is to limit the probability of damage to the building.