Sentence 9.29.7.3.(1)

  1. OS2
  2. OS1
  3. OH1
  4. OP2

Objective

OS2 Structural Safety

Attribution

Intent

Intent 1:

To limit the probability of inadequate support for hardboard interior finishes, which could lead to an inability to resist expected impact, gravity or lateral loads.

This is to limit the probability of the deformation or detachment of interior finishes, which could lead to:

  • where interior finishes contribute to the required bracing or lateral support for studs, the buckling or racking of walls, which could lead to structural failure, or
  • where interior finishes support or provide the substrate for required environmental separation elements, the excessive deformation, displacement or failure of such elements, which could lead to deterioration, which could lead to further compromised structural integrity.

This is to limit the probability of harm to persons.

Top of Page