Sentence 9.30.6.1.(1)

  1. OS3
  2. OH1
  3. OS2

Objective

OS2 Structural Safety

Attribution

[F81-OS2.3]Applies where finished flooring is required to provide water resistance.

Intent

Intent 1:

To limit the probability of inadequate support for ceramic tile, which could lead to the cracking of finished flooring.

Where finished flooring is required to provide water resistance, this is to limit the probability of the ingress of water into the underlay or subfloor, which could lead to the accelerated deterioration of the floor assembly, which could lead to an inability to resist expected gravity loads, which could lead to structural collapse, which could lead to harm to persons.

Top of Page