Sentence 9.15.2.2.(3)

  1. OS2
  2. OP2
  3. OH1
  4. OH4
  5. OS3
  6. OS2
  7. OP2
  8. OH1
  9. OH4
  10. OS3
  11. OS2
  12. OP2
  13. OH1
  14. OH4
  15. OS3

Objective

OP2 Structural Sufficiency of the Building

Attribution

(c) [F20-OP2.1]
(c) [F61-OP2.4]
(c) [F20,F61-OP2.3]Applies to elements that support or are part of an environmental separator.

Intent

Intent 1:

To limit the probability that the inappropriate placement of grout will lead to the inadequate performance or premature failure of concrete block foundation walls under expected environmental or structural loads.

This is to limit the probability of:

  • compromised structural integrity of masonry construction,
  • where masonry construction is part of an environmental separator, the displacement or failure of required environmental separation elements, which could lead to deterioration,
  • in assemblies exposed to moisture or the exterior, damage and deterioration, or
  • an inability to resist expected loads, which could lead to
    • the excessive movement or deformation of walls, or
    • the excessive deflection or vibration of floors.

This is to limit the probability of:

  • the space being unsuitable for its intended use,
  • compromised operation of windows or doors, or
  • damage to the building.
Top of Page