Intent 1:
To limit the probability of insufficient horizontal
reinforcement or that the horizontal reinforcement will not be adequately
encased and bonded to the concrete, which could lead to the cracking
of foundation walls due to temperature changes and shrinkage.
This is to limit the probability of compromised structural
integrity, which could lead to:
- structural failure,
- where elements support or are part of an environmental
separator, the displacement or failure of required environmental separation
elements, which could lead to the deterioration of building elements,
or
- an inability to resist expected loads, which could lead
to
- the excessive deformation or deflection of walls, or
- the excessive deflection or vibration of floors.
This is to limit the probability of:
- the space being unsuitable for its intended use, or
- damage to the building.