Objective

OP2 Structural Sufficiency of the Building

Attribution

Intent

Intent 1:

To limit the probability that moisture-content-related soil movement or the weathering of pyritic material will lead to the heaving or subsidence of floors-on-ground, which could lead to:

  • the failure of floors-on-ground, or
  • the compromised structural integrity of floors-on-ground, which could lead to the ingress of moisture from the ground, which could lead to the deterioration of building elements.

This is to limit the probability of damage to the building.