Objective

OP2 Structural Sufficiency of the Building

Attribution

[F20,F21-OP2.3]Applies to elements that support or are part of an environmental separator.

Intent

Intent 1:

To limit the probability of:

  • an excessively high cement/aggregate ratio, which could lead to poor workability, excessive compressive strength and attendant high shrinkage, which could lead to cracking of grout, or
  • an excessively low cement/aggregate ratio, which could lead to weak, porous grout and inadequate bonding with masonry units and reinforcing steel.

This is to limit the probability of:

  • compromised structural integrity of masonry construction,
  • where masonry construction is part of an environmental separator, the displacement or failure of required environmental separation elements, which could lead to deterioration,
  • in assemblies exposed to moisture or the exterior, damage and deterioration, or
  • an inability to resist expected loads, which could lead to:
    • the excessive movement or deformation of walls, or
    • the excessive deflection or vibration of floors.

This is to limit the probability of:

  • the space being unsuitable for its intended use,
  • compromised operation of windows or doors, or
  • damage to the building.