Sentence 9.12.4.1.(1)

  1. OH1
  2. OS2
  3. OP2
  4. OH2
  5. OS3

Objective

OP2 Structural Sufficiency of the Building

Attribution

[F21-OP2.3]Applies to elements that support or are part of an environmental separator.

Intent

Intent 1:

To limit the probability of excessive soil settlement beneath foundation footings, which could lead to:

  • structural damage to foundations or damage to foundations' moisture-control elements, or
  • where settlement occurs at water-service locations, the rupture of water lines, which could lead to leakage and undermining of the foundation, which could lead to the structural failure of foundations and superstructures.

At sewer-line and water-service locations, this is to limit the probability of compromised structural integrity, which could lead to:

  • structural failure,
  • for environmental separators or elements supporting an environmental separator, the displacement or failure of required environmental separation elements, which could lead to the deterioration of building elements, or
  • an inability to resist expected loads, which could lead to
    • the excessive deformation or deflection of walls, or
    • the excessive deflection or vibration of floors.

This is to limit the probability of:

  • the space being unsuitable for its intended use, or
  • damage to the building.